Hello Experts,

We have a problem where no Accounting Tab appears in the project snapshot.

Is this standard behaviour or are we missing something here?

Thank you.

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

1 Answer

  • Best Answer
    Aug 27, 2009 at 11:31 AM

    Hi,

    this is standard behaviour as the accounting side (FIN/CO) in ERP does not provide snapshot functionality.

    Kind regards,

    Florian

    Add comment
    10|10000 characters needed characters exceeded

    • Former Member Former Member

      Hi Florian

      I am also interested.

      I can compare dates , work...but I don't know how to compare costs, the only way I know is generating a controlling version with these costs and upload to the item... but this is not a very good solution.

      Thanks,

      Sara