on 08-27-2009 6:48 AM
Hi All,
The assessment cycles are configured in the Development system. The transport created was released to integration and quality. We found that the segment do not reflect the way it is in Development system.
We want to transport the configurations once again.
Can anyone tell how the cycle needs to be included in the transport?
Thanks,
Hi,
Go to OKE8 transaction and select the option of transporting the cycles (assessment and/or distribution).
Regards,
Eli
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
Run TCode OKE5 - Transport : Controlling Settings
If your Assessment Cycles are Plan cycles then go to Planning2 tab, select Assessment. For actual cycles go to Actual postings 1 tab and under Cycles select Assessment.
Then click Include in Request (Shift+F6) button. All assessment cycles for your Controlling Area get included in the transport request.
If you do not want all to be transported, then Goto SE10 TCode and display the request. Then double click the task to select the objects. Double click on Table Contents and click Change button. Then delete the entries that you do not want. Save the request and release transport request.
Hope this helps.
Thanks,
Sanjib
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
108 | |
12 | |
11 | |
6 | |
5 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.