on 08-27-2009 3:26 AM
Hi All
I have PO with Account Assignment Type "Q", I want to Goods Receipt to Project Stock.
I think Project Stock and Plant Stock is difference and Plant Stock don't include in Project Stock.
But when I Goods Receipt by MIGO, I have to input Plant and Storage Location.
Could you please how to configure to Goods Receipt without Plant and Storage Location.
Thanks and Best regards,
hi
even though it asks for a Plant and Storage Location.
the stock will be available as special stock against the WBS element only.
the issues also will be against the WBS element only.
carry forward your transactions.
Its SAP Standard process.
Edited by: AP on Aug 27, 2009 6:32 AM
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
108 | |
12 | |
11 | |
6 | |
5 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.