Cost in CN47N

Former Member
0 Kudos

How can I get Actual cost and Palnned cost associated with a Network Activity in this transcation. I have created a layout which gets downloaded as an excel report. Which foelds should I choose in the layout , so that the cost information also shows up.

Thanks,

NM

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

hi,

i believe you cannot display the costs in cn47n

unless you create a means such that the planned and actual costs will be posted into the user fields

(can you perhaps use substitution perhaps to input the planned cost in a user field - ex, qty x price ? )

if you can, then you just display the user field...

however better if you use cost reports, anyway you can do reporting across different projects...

Answers (3)

Answers (3)

Former Member
0 Kudos

Thanks Ramesh and Virendra for your response. If cost cannot be seen in CN47 N, which transaction would give a comparison between Planned and Actual cost for Network Activities ?

Thanks!

Former Member
0 Kudos

Hi NM,

You can check the Plan/Actual details at activity level in CN41 and CN41N transactions. you can check in Hierarchial reports under costs in PS information system. I guess network is activity account assigned in your case !!

Hope this helps you !

Br

Hari.

virendra_pal
Active Contributor
0 Kudos

hierarchy txn S_ALR_87013532

cost element txn S_ALR_87013542

virendra_pal
Active Contributor
0 Kudos

cn47n is an individual overview report and is not what I would use for plan and actual cost

in the activity the plan could be work, material and so on - however the standard price or valuation of the material and activity pricing rates are stored in controlling in different tables

Former Member
0 Kudos

hi,

i believe you cannot display the costs in cn47n

unless you create a means such that the planned and actual costs will be posted into the user fields

(can you perhaps use substitution perhaps to input the planned cost in a user field - ex, qty x price ? )

if you can, then you just display the user field...

however better if you use cost reports, anyway you can do reporting across different projects...