on 08-26-2009 6:41 PM
Hi experts,
Is there anyway to have a check while saving the project in CJ20N that the rolled up cost of the top WBS is equal to the Budget allocated to the top WBS?As for my client the Budget allocation at top WBS and Project cost planning further down the structure are with two different departments,They always want both the values to be same.So if the Project engineer plans the cost in the project it should total up and match the budget at top WBS..
Suggestions please
hi,
if you want original budget to be always equal to planned cost, you need to let ABAPer create a program that would automatically maintain the values from planned cost to original budget..
or else you need to maintain in CJ30 my copying the planned budget.. you can use Edit > copy view then select from total planned cost.
regards.
ramesh
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
hi,
if you want original budget to be always equal to planned cost, you need to let ABAPer create a program that would automatically maintain the values from planned cost to original budget..
or else you need to maintain in CJ30 my copying the planned budget.. you can use Edit > copy view then select from total planned cost.
regards.
ramesh
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
Standard Business practice generally followed is Planning first and Budgetting Next.
And Allocated Budget generally will be at the most equal to the total planned value or less.
In your scenario , is it not possible to adopt the same.
That for a project , planning department do the cost planning first then budgettting department allot budget accordingly.
In such case, in CJ30 , they can copy total planned value as is. Budget allocation then becomes simple.
Thanks
Saikishore.Ganga
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
Standard Business practice generally followed is Planning first and Budgetting Next.
And Allocated Budget generally will be at the most equal to the total planned value or less.
In your scenario , is it not possible to adopt the same.
That for a project , planning department do the cost planning first then budgettting department allot budget accordingly.
In such case, in CJ30 , they can copy total planned value as is. Budget allocation then becomes simple.
Thanks
Saikishore.Ganga
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
hi
if the budget availability control is set. the system defintely check for the value of total and it will not allow more than that cost.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
88 | |
7 | |
6 | |
4 | |
3 | |
3 | |
3 | |
3 | |
3 | |
2 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.