Skip to Content
0
Former Member
Aug 26, 2009 at 04:48 PM

work center formulas

142 Views

Hi, we created actvity type 1,2,3,4,5,6 with op17 and op21 and assigned to std paramer key sap2. now we can see all six parameters with formulas in basic data view, default values view and in costing view. but in scheduling and capacity view, there is no options to enter all formulas for all 6 activities. in scheduling only setup and processing formulas are there. in that case, how to maintain the formulas for remaining 4 activities. same thing for capacity view. say activity type 4 is for loading time, how to capture this capacity and scheduling time without formula. pls advise.