ESS NWDI move from DEV to QA?

We have configured NWDI for DEV and QA, I have released the changes from NWDS and all released transports from Consolidation tab are imported and then in the Assembly tab we have assembled successfully. We could now see the new ESS sca file in the file system.

We don't want to do manually SCA deployment to QA. How do we now move to QA automatically? If I proceed to the next tab in CMS which is Approve tab, do I select all rows and click approve? Please let me know.

We have configured our CONS runtime system as our QA system. The following are the runtime system(RTS) that is configured in our landscape

DEV RTS - DEV

CONS RTS - QA

TEST RTS - Acceptance

PROD RTS - PROD

Thanks

Praveen

Edited by: Praveen11 on Aug 26, 2009 1:12 PM

Add a comment
10|10000 characters needed characters exceeded

Related questions

1 Answer

  • Best Answer
    author's profile photo Former Member
    Former Member
    Posted on Aug 26, 2009 at 12:01 PM

    Hi Praveen,

    As per your post, in CMS immediately after the Assembly'' tab you have the 'Approval' tab. But if in the landscape configurator view of CMS, in the 'Runtime Systems' tab you have configured your 'TEST SYSTEM', then there will be 'Test' tab in between 'Assembly' and 'Approval' tab. You have to specify the SDM host / port in RTS tab of CMS. Immediately the 'Test' tab will be visible in transport Studio of CMS.

    Once that tab is visible, you will see the new ESS sca file (assembled in previous step) in the 'Waiting for import' status.

    Click on import button and the sca will be available in the respective system. This sca is deployed as per the test system parameters specified in RTS of landscape configurator of CMS.

    Similarly in RTS if you specify the SDM host/ port for production system in the 'Production System' section, a tab by name 'Prod' will be shown in the transport studio after 'Approval' tab.

    Hope this helps.

    Thanks.

    Sonali.

    Add a comment
    10|10000 characters needed characters exceeded

    • Former Member Former Member

      Sonali, thank you very much for detailed explanation. You guessed correctly that we have only configured for 2 systems(DEV and CONS) where CONS as QA. We are migrating changes for the first time so we planned to test against QA first then configure TEST and PRD. Anyway understood that TEST and PRD should be configured only then TEST and PRD tabs will be available and components will be migrated.

      For CONS as QA, it worked eventually without going into Assembly tab. Your solution has resolved and clarified my issue.

      There is another thread I posted in different forum with similiar issue also has more information on this topic, could be helpful for someone

      ESS NWDI move from DEV to QA?

      Thanks

      Praveen

Before answering

You should only submit an answer when you are proposing a solution to the poster's problem. If you want the poster to clarify the question or provide more information, please leave a comment instead, requesting additional details. When answering, please include specifics, such as step-by-step instructions, context for the solution, and links to useful resources. Also, please make sure that you answer complies with our Rules of Engagement.
You must be Logged in to submit an answer.

Up to 10 attachments (including images) can be used with a maximum of 1.0 MB each and 10.5 MB total.