on 08-26-2009 7:52 AM
Dear all,
just down i have checked MMSC transcation
for some storage locations MRP indicator is as- 1(storage location stock excluded from MRP)
and this filed is Grayed out, how can make it un-grayed
Regards
kumar
Dear Kumar,
Goto MM02,Enter the material,select MRP4 view,enter the plant and the same storage location for which MRP has been
excluded and enter and now remove the the value 1 from MRP storage location indicator and save the datas,
Save and then check in MMSC
Check and revert back.
Regards
Mangalraj.S
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Dear Kumar,
Go to MMSC_MASS -
> Select Plant , Material & Sloc MRP Indicator & execute with Data Records to be changed option
On the next screen, you will find list of materials as per your selection criteria. On the top you will find Display Old Values option (Green Plus sign icon with page) select it so sytem will show you old values for the Sloc MRP indicator which will show you list of all materials with value 1.
You can set / remove 1 for all materials by changing new value field on the above of material list appearing.
Hope this clarifies your doubt.
Regards,
Tejas
Dear Tejas,
i have executed MMSC_MASS
1) plant
2) stroage location MRP indiactor -1
after executing with the above parameters
i am getting a Message as
You Have Selected up to 1,191,920 Records
we don't have this many materials in our plant
what could be the reason.
Regards
kumar
Edited by: kumar kumar on Aug 26, 2009 11:56 AM
Dear Kumar,
The no of materials which will be displayed is as per your selection criteria i.e. you have these many no of material with stor locn MRP indicator existing with 1 value.
The value is coming large because one material is extended to multiple storage locations.
Hope this clears your doubt.
Regards,
Tejas
Kumar,
This gets derived based on the defination from the SPRO. SPRO->Production Planning->MRP->Planning->Define storage location MRP per Plant.
Hope this helps...
Regards,
Prasobh
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Kumar,
When you are extending the storage location for the first time, default system would propose based on the OMIR definations, before saving itself you can remove the "1" defination and save. Once you have saved with defination "1", you can remove the defination only from MM02 in MRP4 view, you need to go with organisational level both plant and storage location for this.
Regards,
Prasobh
User | Count |
---|---|
100 | |
12 | |
11 | |
6 | |
6 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.