In ME5A (List Scope 'A'), system is showing PR Release date same as delivery date. E.g., If delivery date given in PR is 31.10.2009, then Release date is also showing as 31.10.2009.
This is happening even for PRs which are not released.
Can any one suggest the solution for this?
Thanks in advance.
Thanks & Regards,
Gopi Chand
Dear,
Try creating query by selecting PR table. The data availabel in table EBAN. Select the appropriate fields and build a query.
PR table (EBAN) Fields with description:
eban-banfn - Purchase requisition number
eban-frgkz - Release indicator
eban-frgzu - Release status
eban-frgdt - Release Date
Do select the other fields if any required.
Regards,
Syed Hussain.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Dear Syed,
Release date = Delivery date - (Planned delivery time + GR Processing time). In this case, I have given delivery date as 15.09.2009, planned delivery date as 10 days and GR processing time as 2 days. Then the Relese date should be : 15.09.2009 - 12 days = 03.09.2009. But it is showing as 05.09.2009. i.e., it is considering only planned delivery time but not GR processing time.
What could be the reason for that?
Thanks & Regards,
Gopi Chand
Dear,
Release date = Delivery date - GR processing time - Planned delivery time - Purchasing dept processing time.
PR date is created date.
Release date = Delivery date - Planned delivery time(Days)
Delivery date = when we want to receive the material ( Exclusive GR process time)
Planned delivery time = From Release date to Delivery date.
The above calculation is standard for Material without MRP.
MRP materials are calculating itself as below.
Planned delivery time = Pick up from purchase info record
Release date = Delivery date - (Planned delivery time(Days) + GR process time)
Delivery date = when we want to receive the material ( inclusive GR process time)
PR date always system date.
Pls. Consider the factory holidays also in calendar.
Regards,
Syed Hussain.
Edited by: Syed Hussain on Aug 25, 2009 3:42 PM
Generally the release date in PR takes the default creation date of the PR.This you can find while creating a PR in the Quantities/dates tab at item details.
Regards,
Indranil
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
hi
PR release date you have to capture form the Item Changes option from main menu.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Dear,
The Release date showing in PR is not the Purchase requsition released for further processing. It represents the :
Purchase Requisition Release Date
Specifies the date on which the purchase order should be initiated on
the basis of the purchase requisition.
The release date is based on:
o The purchasing department processing time defined for the plant
o The planned delivery time from the material master record or
purchasing info record
o The delivery date
o The goods receipt processing time from the material master record
Note
The planned delivery time from the purchasing info record and the GR
processing time are only taken into account if the purchase
requisition was generated via materials planning.
Example
Processing time Planned del. GR processing
Purchasing time time
Release PO Delivery Date
date date date required
Date required: 01.10.2007
GR processing time: 2 days (working days)
Planned delivery time: 10 days (calendar days)
Purchasing dept processing time: 2 days (working days)
For the material to be available on the date it is needed, the purchase
requisition must be released on 13.09.2007 (requirement date less GR
processing time, planned delivery time, and purchasing department
processing time).
Regards,
Syed Hussain.
User | Count |
---|---|
103 | |
12 | |
11 | |
6 | |
5 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.