Skip to Content
author's profile photo Former Member
Former Member

Actual dates should not impact the Network scheduled dates

Hi

I have planned schdeuled dates (Early/latest).

When i am confirming the activity the actual dates get updated

When i schedule the network the scheduled planned dates are recalulated

This should not happen for this client i am working for

The requirement is that the Planned Scheduled should remain fixed and

should only change if duration, relationship etc changes.

I have tried different option to solve this but still no clue

  • Adjust basic date 1, 2, 3 option

  • Shift Order

  • No date Update - this seems to work but not visible in CN22/CN25/CJ20n

Kindly highlight if any of you have come with similar requirement & provided solution to it

Either thru standard functionality, configuration or any development

Cheers

Add a comment
10|10000 characters needed characters exceeded

Assigned Tags

Related questions

4 Answers

  • author's profile photo Former Member
    Former Member
    Posted on Aug 25, 2009 at 04:10 AM

    Hi

    Can you elaborate my below querries which may help in identifying a solution to your issue:

    1. If your client doesn't want the system to consider Actual Dates, why he wants to Re-Schedule?

    2. What he wants to Check/Compare from Network before & after (re)scheduling?

    Regards

    Babu

    Add a comment
    10|10000 characters needed characters exceeded

  • Posted on Aug 27, 2009 at 11:36 AM

    set schedule in past to 999 and then check - this can be done in scheduling parameters for network OPU6

    Add a comment
    10|10000 characters needed characters exceeded

  • author's profile photo Former Member
    Former Member
    Posted on Aug 27, 2009 at 01:56 PM

    Hi Manoj,

    I had the same requirement and able to achieve it by std. settings. Keep in mind that the planned dates wil get changed when you do the final confirmation. You should have the control on the planned dates until the activity get Fianlly confirmed.

    psconsultant

    Add a comment
    10|10000 characters needed characters exceeded

  • author's profile photo Former Member
    Former Member
    Posted on Aug 27, 2009 at 01:56 PM

    Hi Manoj,

    I had the same requirement and able to achieve it by std. settings. Keep in mind that the planned dates wil get changed when you do the final confirmation. You should have the control on the planned dates until the activity get Fianlly confirmed.

    psconsultant

    Add a comment
    10|10000 characters needed characters exceeded

Before answering

You should only submit an answer when you are proposing a solution to the poster's problem. If you want the poster to clarify the question or provide more information, please leave a comment instead, requesting additional details. When answering, please include specifics, such as step-by-step instructions, context for the solution, and links to useful resources. Also, please make sure that you answer complies with our Rules of Engagement.
You must be Logged in to submit an answer.

Up to 10 attachments (including images) can be used with a maximum of 1.0 MB each and 10.5 MB total.