Hi,

I want standard cost with mixed costing ratios(weighed average of production versions) i created productions and assigned material master and created mixed ration with ck94 but when i am runing standard cost it is taking production version 1 default.

What is missing for taking average of 3 production versions?

Thanks in advance

Accepted Solutions (0)

Answers (2)

Answers (2)

former_member184655
Active Contributor
0 Kudos

Dear Padma,

Check this link,

Regards

Mangalraj.S

Former Member
0 Kudos

Hi Mangalraj,

I am unable to see the Weighted Average Standard Cost and standard cost for cost run. i have done following steps

1. we have created 3 production versions and assigned in MRP veiw.

2. created 1 procurement alternative (Procurement) vendor & p.org given.

3. Mintioned the mixed ratios (ck94) PV1 20% PV230% PV25% Procurement 25%

4.Maintained costing version (OKYD) Costing versio 1, cositng type 01, valuation variant ZCP qty structure ZMIX.

5. Standard cost run CK11n

But i am getting standard cost for production version 1 only. where i will get the weighed average stanadard cost?

Is it required to activate the spilt valuation?

Thanks,

Padma

Former Member
0 Kudos

Hi,

You have to define the procurement Alternatives using TCode CK91N. Also, the Quantity Structure Type needs to be maintained.

Thanks,