Hi i have this question:
i have PP order to deliver. Material to deliver is Make to Order in particular for WbE, price control S.
It's the first time a deliver it in the sistem, so Qbew is clean.
I have calculate the standard cost for the material only with ck11n so at divisional level so only Mbew as the standard value that is 100.
My planned cost for the PP order are 110.
What i want to realize is to have a good receipt (MB31) at Mto stock evaluated at standard price 100 and not with planned value 110!!!
The process run as i want if the sistem has already a record in Qbew, but not when is clean!
Thanks.
Paolo