Hello experts,

We have a situation where our product has base UoM as well as alternate UoM maintained in the material master. We allow our customers to use either of these UoM when they order. Those customer who order using alternate UoM, we would like ATP check and confirmation to use alternate UoM instead of base UoM. At present ATP process is based on base UoM so if insufficient qty is available it would confirm incorrect qty for the alternate UoM.

10 |10000 characters needed characters left characters exceeded

Can you post an example for your last sentence

0
* Please Login or Register to Answer, Follow or Comment.

2 Answers

Vijay Bedekar Dec 27, 2016 at 06:40 PM
0

Here is an example:

Available inventory 50EA for LOT-A

Where one case (UoM CS) needs 100EA.

If customer orders 1CS, system would confirm that order item with 0.5CS as there are only 50EA available.

F Y I : SAP has confirmed that this is std ATP functionality, ATP is always based on base UoM.

Share
10 |10000 characters needed characters left characters exceeded
G Lakshmipathi
Dec 28, 2016 at 01:09 PM
0

When SAP have already confirmed how ATP works, not sure, what else you expect from SCN