We have entered a cost center in Maintain Settlement Rule. When we attempt to settle the project in CJ88 using Partial Capitalization, we get error KI235 Account xxxxxx requires an assignment to a CO object. Why will the cost center on the settlement rule not be used?

Accepted Solutions (0)

Answers (4)

Answers (4)

Former Member
0 Kudos

We had to change the field status group that is set in master data for the account. The old group was not allowing the cost center to be used.

Former Member
0 Kudos

Hi kevin where is this field status group that you talked about? I have encountered the same problem, do you mind further elaborating on your solution?

virendra_pal
Active Contributor
0 Kudos

check out oss note 1296568

nitin_patoliya
Active Contributor
0 Kudos

Also check your settlement profile, cost center should be defined as valid receiver

Regards

Nitin P.

Former Member
0 Kudos

Nitin,

In Settlement Profile we have Cost Center set to "Settlement Optional".

Kevin

Former Member
0 Kudos

hi

check the GL account which specified in the error message and double click on the proceed and maintain the default Cost Center and then save and try to do the settlement.

Former Member
0 Kudos

AP,

I do not understand "click on the proceed and maintain the default cost center".

Kevin

Former Member
0 Kudos

Hi Kevin,

Maintain default cost center in the respective Cost Element (G/L acct) Master Data ( Default account assignment tab) in T-code KA02.

Thanks