How to convert non-billable hours to billable in Project system WBS?

47 Views

I have not set the billing element flag for a WBS element. This is a billable WBS and therefore this flag should be set in the beginning. Now all the project time logged with this WBS is marked as non-billable. Now i have marked this WBS as billable but how can i make all the previous time booked under this wbs as billable?

Is there any Standard sap program which is available to convert the previous non-billable hours to billable?