Hi All,
In my DP 5.0, I am trying to run a macro function IS_Initial. WHen i ran this macro in SDP94 interactively in my Qual system, its giving me a short dump with this error. GETWA_NOT_ASSIGNED. Field symbol has not yet been assigned. The current ABAP program "/SAPAPO/SAPLADVF" had to be terminated. What this means ? I am not getting any help on this. Surprisingly, same macro works fine in another Planning Area. But fails in the intended PA. Same thing happening in Dev system too.
I just wanted to show to users, that system can work well with 0 and nothing. So I want to capture 0, if its blank, capture other KF value. But its totally failing, whereas same macro works fine in other PA.
So what could be the reason ? I ran the PA time series const. check too. Still no help. Any suggestions pls ?
thanks
Venkat