Hi all,

Monitoring:

In mdm 5.5 sp6 once you create your repository, how do you monitor it regularly??

lets say i need to upload a excel file every day via import manager and syndicate it.

i schedule it using windows scheduler.

Now,is there any specific location where i can look at whether the my repository is working fine are it is runing through errors?

and Normally how do we monitor a repository ?

Transports:

I learnt that once you create a repository , if you wish to move from ur dev to qa, then..

1) we need to archive the rep,

2) copy the file to archive directory of quality system

3) unarchive in qa

is this the correct way of transportation involved in MDM.(5.5 sp6)??

or do we have any other process to move the repositories?

If you move the a2a file in the above mention way, do our rules, strategies, validations be created automaticallly in qa or we need to create them manually again in qa ??

Thanks in advance

Regards

phani

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

1 Answer

  • Best Answer
    avatar image
    Former Member
    Aug 20, 2009 at 02:38 PM

    Hi Phani,

    For monitoring MDM 5.5 SP06 Repositories, you can use MDM Console, Wily Introscope and Solution Manager.

    - Standard MDM Console guide available on - www.service.sap.com/installmdm

    - https://www.sdn.sap.com/irj/scn/index?rid=/library/uuid/30aa4934-cc63-2c10-0491-d312a106f716

    For moving repository from one environment to other, you can either transfer the entire repository or only the schema.

    Rgds.

    Add comment
    10|10000 characters needed characters exceeded

    • Former Member Former Member

      No transport with the schema option does not transport Matcching strategy and workflows. Validation and assignments are transported with the schema transport.

      best regards

      Ravi