IBP Planning Operators - Can it be triggered via CPI? or any External system?

0 Kudos

Hi,

We have a process of extracting data from BW system going to IBP on a regular basis via CPI. Once the data stored in IBP there is a DISAGG planning operator that will copy and dissaggreate the values to the final key figure visible to the users.

To automate the process we develop a custom program in BW. At the end of the BW process chain there is a program to trigger the CPI tasks automatically to start the extraction. However, this will not trigger the DISAGG operator in IBP.

I am thinking of just scheduling the DISAGG operator to run regularly (i.e. every 15mins).

But there might be a more elegant solution/option for it? Can CPI trigger the planning operators in IBP?

Appreciate your response 🙂

Accepted Solutions (0)

Answers (1)

Answers (1)

sheldon_piao
Advisor
Advisor
0 Kudos

Dear Jerson,

The DISAGG mentioned above is the disaggregation operator in query designer/Modelling Tool, right? Have you tried the standard planning function type '0RSPL_DISTR_KEY' or '0RSPL_DISTR_REFDATA'?

Best Regards,

Sheldon

0 Kudos

Hi Sheldon,

No. I am referring to the DISAGG operator in IBP system "Copy and Disaggregate Key Figure Operator"

Regards,

Jerson Durens

sheldon_piao
Advisor
Advisor
0 Kudos

Hi Jerson,

Can you provide the screenshots for it?

Best Regards,

Sheldon