Dear All,

My client is having a process in which while downloading KOB1 the system is giving report of all the process orders wise activities confirmed in that month against some cost center.

Now when i am going into line item it takes me to process order confirmation display where activiies to be confirmed and activities yet to be confirmed are displayed.

After that cost center report S_alr_87013611 is displayed wherein actual rates(quantity ) is displayed for that activities.

Now the system shows difference between actual and standard activities.

The difference is the calculated in excel on the basis of KOB1 report and difference is loaded process order wise on calculation done in excel through LSMW (for transaction KB21n) wherein difference quantity is posted from cost center to process order.

Now client needs automation in the sense that no excel calculation should be done and difference should be posted for that month for each process order in the ratio calculated in excel.

Kindly provide any solutions if any, avaliable in standard or Z development has to be done.

Thanks and Regards,