Skip to Content
avatar image
Former Member

QM DIMONNDS

Can any body tell Right solution

1)I created dynamic modification:

i) Iin dynamic modification i assign radio button usage decision level

ii)reset period 1

iii)stage 1 ins 004 ist X details no inspection 1 new inspection stage 99, rejection 1,new inspection stage

iv)ok

no of skips 98, duration 5 new insepction stage 99

if not ok

rejections 1 , new inspection stage 1.

i created dynamic modification rule ( my requirement is one inspection lot for daily against vendor)

2) in material master i assignmed dynamic modification rule and tick the check box skip allowed

3) in quality plan header i maintained dynamic modificiation lot level

now i will do gr one purchase order against 10 recipts

system generate 10 lots ,that first lot i have to assign specification and sample and give the result and give usage decision.

and second inspection lot while i am assign the sample system suggest lot is skip but direct posting will do in usage decision.

my query is i want only one inspection lot against material for particular date & material only i post to quantity first lot

remaining lot i dont what to post manually.

if it is possible in standards give ur valuble soloution .................I will appriciate those guys.

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

2 Answers

  • Best Answer
    avatar image
    Former Member
    Aug 18, 2009 at 08:21 AM

    Hi

    In short as you have specified the reset period as 1 day,.......

    System will reset the DMR Every day.

    Now suppose 10 lots created.you only want to Inspect first lot.rest should be skipped.(auto UD)

    then whatever setting you have done ,addition to that

    maintain:

    1.QA16 create varient

    2.QA17 schedule it for say 1 hr.

    3.in plant level enter maximum skip duration & UD period as 1 hrs.

    4.click on Auto UD & skip in QM view.

    After these settings first lot will come in QI stock & rest will be Auto UD in a day.

    I hope this will help

    Regards

    Sujit S Gujar

    Add comment
    10|10000 characters needed characters exceeded

    • Former Member Former Member

      Thank u responding

      yes i created only one group same group counter i assigned all vendors

      because all vendors have same specifications....why i should go for different group counters,if any alternate solution is there tell me i will appriciate.

  • avatar image
    Former Member
    Sep 01, 2009 at 01:10 PM

    i will give Revert back

    Add comment
    10|10000 characters needed characters exceeded