Dear All,

Please explain me that can i use strategy 20 for make to order and also for generating plan order from PIRs.

Bcoz i alreadt tested it with this strategy, it is generating plan orders from sales order and also from PIRs.

But i want to have some senior's recommendations to use it.

is there any drawback to use it for both.

My scenario is that: industry is pure make to order. but they want to plan two raw materials(Imported materials) at the start of year and then after analyzing the planned order qty, they will delete PIRs.