on 08-16-2009 8:49 AM
dear all:
In report CJI3, there is no option of the "profit center" in the column set, how to add it?
Thank you!
Create actual cost report using CJE1 with one of the selection characteristics as profit center.
Execute this report with CJE0 this with give a report on actual cost using based on PC. To display the actual cost line items, just select the PC line item and GOTO > CALL UP REPORT > LINE ITEMS > PROJECT ACTUAL COST LINE ITEMS.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi
Use Dynamic Selection function --> Org. Units WBS Element --> Profit Center for your Requirement
But limitation is you can just filetered out output for Particular PC and you will not get Profit Center column in O/P.
Such limitation is exists for Other WBS Related (PRPS) field also.
Hope this will help you.
Regards,
Swapnil Kharul
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
The dynamic selection will only restrict the slection of project object based on provided profti centre in input.
I fill that you wanted to sort CJI3 after executing report based on profit center. As the profit center is not available in Cji3 change layout, You can add the same using COOMEP01 (Function Module EXIT_SAPLKAEP_001: Line Item Reports in Actual: Customer-Specific Fields).
Based on which object type i.e WBS, NWA Production order , you wanted to disaply profit center you have to provide to your ABAPer.
I have used this approch. If you serach for relvent note, you will get this userexit.
With Regards
Nitin P.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi;
inside CJi3 there is no field for PROFIT CENTER.
Any how if you want to restrict your report on some specific profit center's then prior to execution choose: (Shift + F4) Dynamic Selection >> Org. Units WBS element >> Profit Center.
So like this you will be able to get your out put on the selected profit centre's.
Hope this will help.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi...........
after Executing in CJI3.
Go to..................Settings..layoutchange...........find and add profitcenter.....then ok.
I hope it will solve
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
91 | |
7 | |
7 | |
4 | |
3 | |
3 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.