Del complete indicator reset in PO

Hello Experts,

PO qty =20 , delivered =10

I set Delivery indicator =x in po , In PO it shows open po qty(deliv sched tab) =0 ,

I can still post GR for remainining quantity =2 till this part its ok but after posting GR , system is resetting Delivery completed

indicator & also showing open po qty=8 in PO. is this the normal SAP behaves ...

after this I can see in all reports ME2M/N/L it is showing open order qty that is obvious because del completed indicator is reset..

Thanks for Your expert comments..

John

Add a comment
10|10000 characters needed characters exceeded

Related questions

2 Answers

  • Best Answer
    author's profile photo Former Member
    Former Member
    Posted on Aug 16, 2009 at 08:59 AM

    check for over/under delivery tolerances as well .. make them zero and then try.

    Add a comment
    10|10000 characters needed characters exceeded

    • why do you still get quantity after you have closed the order with a delivery complete?

      Yes, SAP removes the delivery complete flag in case

      - your receipt quantity is less the order quantity.

      - you have set teh DCI manually

      - and you do another goods receipt whose quantity is still that low that the order is not reached yet

      - and the total received quantity is still below the tolerances.

  • author's profile photo Former Member
    Former Member
    Posted on Aug 16, 2009 at 11:58 AM

    Hello John,

    When you do GR again, please find the delivery indicator in GR by default will be automatic and hence the system refreshes and changes the setting in PO. So while doing GR, change the delivery indicator "Yes", then check it in PO.

    Hope this will clarifiy.

    Regards,

    Elanchezhian. K.C.

    Add a comment
    10|10000 characters needed characters exceeded

    • Former Member

      When you do GR again, please find the delivery indicator in GR by default will be automatic and hence the system refreshes and changes the setting in PO. So while doing GR, change the delivery indicator "Yes", then check it in PO.

      Dear K C

      I am not getting what should I do for delivery Indicator in GR...

      options available to me are set automati ( default) , set, do not set.

      thanks

Before answering

You should only submit an answer when you are proposing a solution to the poster's problem. If you want the poster to clarify the question or provide more information, please leave a comment instead, requesting additional details. When answering, please include specifics, such as step-by-step instructions, context for the solution, and links to useful resources. Also, please make sure that you answer complies with our Rules of Engagement.
You must be Logged in to submit an answer.

Up to 10 attachments (including images) can be used with a maximum of 1.0 MB each and 10.5 MB total.