Hi Experts,
I am facing a budget exceeding error: Ntwk actvty 6000001 0020 budget exceded year 2009.
following is the settings
Availability control against: Overall
Availability control against: Budget
Availability Control in the Controlling Area Currency:
Activation type: Automatic activation during budget allocation
Usage level in %: 0,00
The project is P.0001
Top lvl P.0001
WBS P.0001.1
Network Activity (External services) 6000001 0010 PR-($40000) PO($20000) & Service entery done with same amount($20000).
Network Activity (External services) 6000001 0020 PR-($1)
Actual $20000
Commitment 20001
Assigned 40001
Available $49
Now we updated the budget as below:
The original budget was 40050 in IM then modified to 45050 and distributed in CJ30.
When we try to update the Service PR with 49 or more dollars, gives error in commitments and when the log checked, the budget exceeding message is there, if the PR updated with 48 USD, it gives the budge is exhausted.
40050(Old Budget)-40001 (assigned) = 49 USD. Which means, the supplement of the 5000USD is not considered.
Run the CJEN and CJBN to reconstruct the project but no use.
Please help me out where to check and what went wrong. its in client prd.
Regards,
Ganesh