material provide to vendor for MRP run

Former Member
0 Kudos

Hi SAP gurus,

How can i consider material provide to vendor for MRP run

Best Regards,

Parag Save.

Accepted Solutions (1)

Accepted Solutions (1)

rupesh_brahmankar3
Active Contributor
0 Kudos

Dear,

The stock of material provided to vendor is managed in a separate MRP area as vendor.

Regards,

R.Brahmankar

Former Member
0 Kudos

Dear R.Brahmankar,

Thanks for reply

But The stock is not at my plant it is available at Material provide to vendor. & not if i have MRP run then it will not consider hte stock.

What I want :

With MRP run The Stock "Material provide to vendor " should consider.

The solution to have it in our own plant dosent sute to my situation

Can there be any other solution

Is there any other config. need to maintain in SPRO to consider Material provide to vendor

Best Regards,

Parag Save

rupesh_brahmankar3
Active Contributor
0 Kudos

Dear,

Special stocks are not considered for MRP run. Subcontracting stock is a special stock(O), hence is not considered for MRP. If you want then you need to create MRP area with subcontract as vendor MRP area.

Planning of the components to be provided for subcontracting Please refer this link for details,

Material Requirements Planning -> Planning Execution -> Material Requirements Planning: Planning of the components to be provided for subcontracting

http://help.sap.com/saphelp_dimp50/helpdata/EN/c4/106956ae8a11d1a6720000e83235d4/content.htm

Regards,

R.Brahmankar

Former Member
0 Kudos

Dear R Brahmankar ,

Thanks a lot

Answers (1)

Answers (1)

Former Member
0 Kudos

Hi,

for ur purpose u need to activate MRP areas for vendors

and u should run MRP at MRP level areas

Regards

kumar