How to change the default date in Person assignment tab?

Former Member
0 Kudos

Hi experts,

Does anyone know how to change the default date in person assignment tab in cj20n? Currently, the system always take the scheduled finish date to the date of the person assignment tab. Can I change it to the start date?

Thanks and rgs,

Michelle

Accepted Solutions (0)

Answers (2)

Answers (2)

Former Member
0 Kudos

Hi Michelle,

Goto SPRO->Project system->Dates->Scheduling->Specify Parameters for Network Scheduling, Here you can control the workforce planning dates.

Hope this is useful...

Regards

Aatish

nitin_patoliya
Active Contributor
0 Kudos

Yes you can chagne it.

With regards

Nitin P.

Former Member
0 Kudos

Hi Nitin,

Can you please elaborate how can I achieve this purpose? Any tcode to use? or path in SPRO.

Rgs, Michelle

nitin_patoliya
Active Contributor
0 Kudos

I am not exaclty able to tell from where it picks the date, just sharing with you my understading. Normally persona assignment tab appears for hte activit in cj20n after you give workcenter / work filed in the activity . So, from work center master data seeting / capacity seetings these date mostly will originate.

With Regards

Nitin P.

Former Member
0 Kudos

Thanks Nitin! It's controlled by the distribution key which is assigned to the work center.

Edited by: Michelle Sun on Aug 14, 2009 10:24 AM

Former Member
0 Kudos

issure resolved