MRP plans Sales order for Finished Goods Outside planning horizon even when using NETPL. Strategy 40 is in use with 3 level BOMs. Planning horizon - 200 day. How could it be prevented?
by any chance does your total lead time exceeds than 200 days ?
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Dear,
Please check have you assigned any MRP group to your material masters in MRP1view? Then check the planning horizon maintain in MRP group in OPPR also check same for your plant in OPPQ.
If you define it as 200 days then system will only plan the requirement which falls under 200 days with processing key as NETPL.
If we set planning horizon as 200 days then in the material in which MRP relevant changes happened in last 200 days will only be planned. Planning horizon is the period beyond it, requirements don't generate planned orders
Please check and revert back.
Regards,
R.Brahmankar
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
99 | |
11 | |
11 | |
6 | |
6 | |
4 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.