MRP plans sales orders outside planning horizon

MRP plans Sales order for Finished Goods Outside planning horizon even when using NETPL. Strategy 40 is in use with 3 level BOMs. Planning horizon - 200 day. How could it be prevented?

Add a comment
10|10000 characters needed characters exceeded

Related questions

2 Answers

  • Posted on Aug 14, 2009 at 04:40 AM

    Dear,

    Please check have you assigned any MRP group to your material masters in MRP1view? Then check the planning horizon maintain in MRP group in OPPR also check same for your plant in OPPQ.

    If you define it as 200 days then system will only plan the requirement which falls under 200 days with processing key as NETPL.

    If we set planning horizon as 200 days then in the material in which MRP relevant changes happened in last 200 days will only be planned. Planning horizon is the period beyond it, requirements don't generate planned orders

    Please check and revert back.

    Regards,

    R.Brahmankar

    Add a comment
    10|10000 characters needed characters exceeded

  • author's profile photo Former Member
    Former Member
    Posted on Aug 14, 2009 at 05:14 AM

    by any chance does your total lead time exceeds than 200 days ?

    Add a comment
    10|10000 characters needed characters exceeded

Before answering

You should only submit an answer when you are proposing a solution to the poster's problem. If you want the poster to clarify the question or provide more information, please leave a comment instead, requesting additional details. When answering, please include specifics, such as step-by-step instructions, context for the solution, and links to useful resources. Also, please make sure that you answer complies with our Rules of Engagement.
You must be Logged in to submit an answer.

Up to 10 attachments (including images) can be used with a maximum of 1.0 MB each and 10.5 MB total.