08-13-2009 2:31 AM
Hi All
The BD21 transaction code is used for transfer the data between the two system by change pointer.
is it possible to setting the cost center ranges In BD21 transaction code.
Please Confirm
Thanks & Regards
K.Gunasekar.
08-13-2009 6:21 AM
Yes, it's possible to use change pointers for cost center master.
08-13-2009 9:58 AM
Hi All
I am planning to schedule the COSMAS report in background mode by using Varient.
is it possible to setting the cost center message type COSMAS varient ranges In BD21 .
Thanks & Regards
K.Gunasekar.
08-13-2009 12:17 PM
yes, if the message type COSMAS activated for change pointer the you can schdule the job to create an Idoc.