Dear All,

Kindly advice. Can we make a project with 3 company codes different? How can we structure it?It will have 3 different settlement to cost center.

Can we do like :

Project Definition - Company code A /Plant A1

WBSE level 1 - Co. code A/Plant A1

WBSE level 2 - Co. code A/Plant A1

WBSE level 3 - Co. code A/Plant A1 (settle to cost center A)

Network header & activity

WBSE level 3 - co.code B/Plant B1 (settle to cost center B)

Network header & activity

WBSE level 3 - co.code C/Plant C1 (settle to cost center C)

Network header&activity.

*. Is there any way to transfer cost between WBS to WBS or network to network?

Please advice.

Nies

Edited by: Denis Evitanto on Aug 12, 2009 4:34 PM

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

2 Answers

  • Best Answer
    avatar image
    Former Member
    Aug 12, 2009 at 02:39 PM

    Hi Denis,

    You can create a project with 3 company codes and w.r.t 3 plants. but all 3 company codes must assigned to single controlling Area. In PS CO Area is the highest Org Element. you can build project with 3 different company codes but make sure all networks with 3 different plants must be assigned to the 3 different WBS Elements of having those 3 plants. you dont maintain defult settlement rules for those WBS Elements. you have to manually maintain Settlement rules w.r.t receiver C.C.

    Hope this helps you !!

    Br

    Hari.

    Add comment
    10|10000 characters needed characters exceeded

    • Former Member Former Member

      Hi Nies,

      You dont maintain network profile in project profile and select manually the relevant Network type while creating and you can select plant as well as per your requirement.

      You can assign plant w.r.t report requirement at project definition level. anywhys you are not going to do any procurement process at that level but you must maintain proper plant to respective WBS Elements as per your requirement. you dont maintain any default values in project profile and in network profile.

      Br

      hari

  • avatar image
    Former Member
    Aug 12, 2009 at 02:40 PM

    Hello

    You can do that as far as your 3 company codes are assigned to same controlling area and Cctrs are maintained in tht controlling area.