ABAP +JAVA system copy process

Hello All,

We are in process of building a server from a existing ECC 6.0 ABAP + JAVA system.

We are using system copy process where we are restoring ABAP databse from source system.

My question is about the JAVA part.

How can we copy java part? Can we export only JAVA part from ECC 6.0 ABAP +JAVA system and import this to target server.

Please suugest the process.

Regards,

Manish

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

4 Answers

  • avatar image
    Former Member
    Aug 12, 2009 at 07:39 PM

    Hi,

    You can export JAVA stack but u need to select the JAVA Schema while ur exporting the java DB for more info go through the system copy guides.

    Regards

    Naresh.

    Add comment
    10|10000 characters needed characters exceeded

  • avatar image
    Former Member
    Aug 12, 2009 at 01:59 PM

    Manish,

    Are you using the SAP inst tool for system copy?

    Then we can take both ABAP+JAVA export. Instead of taking ABAP and Java Seperately.

    Regards,

    Raja. G

    Add comment
    10|10000 characters needed characters exceeded

  • avatar image
    Former Member
    Aug 12, 2009 at 02:42 PM

    Hi Manish,

    Running SAPNIST is a must for ABAP+JAVA instance system copy process.

    If you are using the backup/restore for the ABAP schema, then -

    Yes, You should also perform the Java export (on the source system).

    {Eg. Additional Software Lifecycle Tasks -> System Copy -> Oracle -> Source System -> Central System à Database and Central instance Export. Just select the Java Schema for the export}.

    This java export directory can be used during the sainst run. (sainst will ask for the export location. At that point, enter the Java export location)

    At a point, the sainst will ask you to perform the DB restore and you can perform the restore that time.

    Hope this helps!

    Regards,

    Raj.

    Add comment
    10|10000 characters needed characters exceeded

  • avatar image
    Former Member
    Aug 12, 2009 at 04:09 PM

    Refer to homogeneous system copy guides from the attached link.

    [System Copy and Migration]