Hi all,

i have a scenario like when a event raised then based on date entered by user after that date only i need to start processing that task and it can be 1 month ,so requested start can be set like 1 month etc,.

my doubt is can i go for workflow using requested start or it will be performance issue for time gap in months?

Please suggest,

Regards,

Rajkumar

Add a comment
10|10000 characters needed characters exceeded

Assigned Tags

Related questions

5 Answers

  • Best Answer
    Posted on Aug 11, 2009 at 10:43 PM

    Hello,

    I don't understand your requirement but anyway a Requested Start deadline of 1 month will not cause a performance issue.

    regards

    Rick Bakker

    Hanabi Technology

    Add a comment
    10|10000 characters needed characters exceeded

  • author's profile photo Former Member
    Former Member
    Posted on Aug 12, 2009 at 03:58 AM

    There will be no performance issue. You can go by the requirement.

    Thanks

    Arghadip

    Add a comment
    10|10000 characters needed characters exceeded

  • author's profile photo Former Member
    Former Member
    Posted on Aug 11, 2009 at 11:05 PM

    Yes, you can use the date entered by the user as the requested start date. As far as performance goes, it will not really effect performance since no task or background job is being executed until after the deadline is reached. However, I would suggest having a maximum number of days the user can enter. You don't want a WF sitting in a waiting status for too long. My personal rule of thumb is that a WF should be started and completed within 30 days. Any (single) business process that takes longer than that to complete perhaps need to be redesigned.

    Derrick

    Banks & Company, LLC

    Add a comment
    10|10000 characters needed characters exceeded

  • author's profile photo Former Member
    Former Member
    Posted on Aug 12, 2009 at 03:51 AM

    Hi Raj,

    As such there will be no performance issue as far this standalone workflow is consisdered....but there is some thing which might get affected in overall system.

    Suppose everday 50 instances of this same workflow are being generated................................and after 29th day we will have nearly 50*29 = 1450 active instances in system.So this will put verload impact on system and none of the wokflow instances are not completed as such.

    Add a comment
    10|10000 characters needed characters exceeded

  • author's profile photo Former Member
    Former Member
    Posted on Aug 12, 2009 at 06:32 AM

    Thanks for all good advices...

    Add a comment
    10|10000 characters needed characters exceeded

Before answering

You should only submit an answer when you are proposing a solution to the poster's problem. If you want the poster to clarify the question or provide more information, please leave a comment instead, requesting additional details. When answering, please include specifics, such as step-by-step instructions, context for the solution, and links to useful resources. Also, please make sure that you answer complies with our Rules of Engagement.
You must be Logged in to submit an answer.

Up to 10 attachments (including images) can be used with a maximum of 1.0 MB each and 10.5 MB total.