Update Account Assignment in Location Tab

I want the account assignment, e.g. cost center in the PM order Location tab to be updated when a user changes the settlement rule. This defaults from the object, e.g. functional location but isn't changed when a user updates the settlement rule.

Is there any config to do this?

Question 2: Which table field stores the settlement rule cost center.

Thanks

Add a comment
10|10000 characters needed characters exceeded

Related questions

3 Answers

  • Best Answer
    author's profile photo Former Member
    Former Member
    Posted on Aug 11, 2009 at 09:27 AM

    It seems that you want to update the Cost center of the Equipment / Functional location master with Cost center given in the Setttlement Rule (transaction).

    Changing master data based on the data in transaction, I think it is not possible.

    Babu

    Add a comment
    10|10000 characters needed characters exceeded

    • Former Member Former Member

      I think, It's better not to maintain Cost Center in Equipment/Func Loc, also you can opt to maintain settlement rule in Maintenance Plan.

      If client insists on maintaining the cost center information in Equipment u may/can use Sort Field for information purpose.

  • author's profile photo Former Member
    Former Member
    Posted on Aug 12, 2009 at 08:59 AM

    Hi

    Why the settlement rule is changed?

    Regards

    Manish

    Add a comment
    10|10000 characters needed characters exceeded

    • Former Member Former Member

      Hi

      I believe that settlement rule is created during the Order release.

      Tell user to enter the CC in the location tab in CC field ( In Maintenance order) , before the order release. And then release the order. This CC will get copied in settllement rule.

      In thias way, you will find the same CC in the location tab and in settlement rule.

      Regards

      Manish

  • author's profile photo Former Member
    Former Member
    Posted on Aug 12, 2009 at 09:33 AM

    Hi,

    Pass PM Order Obj no to COBRB table to get the cost centre & settlment details.

    I think you need to review your logic as it is always possible to make settlment in % to more than one cost centre.

    Ramesh

    Add a comment
    10|10000 characters needed characters exceeded

    • Former Member

      Thanks to Chandrashekar and Ramesh, I read this from COBRB, and this worked. No noeed to update acc assignment CC.

      Didn't want to force users to change the CC in the location tab as there were bound to be mistakes etc.

      thanks all.

Before answering

You should only submit an answer when you are proposing a solution to the poster's problem. If you want the poster to clarify the question or provide more information, please leave a comment instead, requesting additional details. When answering, please include specifics, such as step-by-step instructions, context for the solution, and links to useful resources. Also, please make sure that you answer complies with our Rules of Engagement.
You must be Logged in to submit an answer.

Up to 10 attachments (including images) can be used with a maximum of 1.0 MB each and 10.5 MB total.