Dear Experts,

My client has executed the Costing Run for July 09 (CK40n) and now they want to check Product wise Activity Prices. For example they have Labour, Electricity, Machinery etc defined as separate activity types. Is there any T. Code or Report wherein we can check the product wise costs for these activities.

Thanks in advance,

Amarendra

Add a comment
10|10000 characters needed characters exceeded

Assigned Tags

Related questions

3 Answers

  • Posted on Aug 11, 2009 at 08:45 AM

    Hi ,

    Create a Summarization hierarchy using transaction KKR0. Include Product ( Material ) as a Summarization characteristic along with other characteristics like Plant , Co Area etc., Carry out Data collection using transaction KKRC. Use any of the Standard reports in Cost Object Controlling Info systems and there you would find sum total of activity cost per each individual product.

    Regards,

    Venkat.

    Add a comment
    10|10000 characters needed characters exceeded

  • Posted on Aug 11, 2009 at 10:05 AM

    Dear Amarendra,

    For individual materials you can get the splitup using the Code CK13N or else you click on the current period icon in the material

    master in the costing 2 view.

    Or else check these reports S_ALR_87099932 and S_P99_41000111,after executing the report click on change layout and

    select the required fields.

    Regards

    Mangalraj.S

    Add a comment
    10|10000 characters needed characters exceeded

  • author's profile photo Former Member
    Former Member
    Posted on Aug 12, 2009 at 04:44 AM

    Hi,

    Use T.Code CK80_99 for analyising cost component split

    regards

    srikanth

    Add a comment
    10|10000 characters needed characters exceeded

Before answering

You should only submit an answer when you are proposing a solution to the poster's problem. If you want the poster to clarify the question or provide more information, please leave a comment instead, requesting additional details. When answering, please include specifics, such as step-by-step instructions, context for the solution, and links to useful resources. Also, please make sure that you answer complies with our Rules of Engagement.
You must be Logged in to submit an answer.

Up to 10 attachments (including images) can be used with a maximum of 1.0 MB each and 10.5 MB total.