    Posted on Aug 11, 2009 at 06:10 AM

    Hi

    The Final Preparation phase also serves to resolve all critical open issues.

    It means whatever open issues you have find out in testing or may be in data migration needs to be resolved in this phase only.

    Add a comment
    10|10000 characters needed characters exceeded

  • author's profile photo Former Member
    Former Member
    Posted on Aug 11, 2009 at 05:45 AM

    Realization phase - You have to customized the SAP to the busniness as discuss in Blueprint. here also invlove is custom development and testing .

    final prepartion phase : In this u take all the request to production, prepare all the data migration activity. Keep all the master data and transaction data ready in given formats and load them.

    Add a comment
    10|10000 characters needed characters exceeded

  • author's profile photo Former Member
    Former Member
    Posted on Aug 11, 2009 at 05:47 AM

    Realization: The purpose of this phase is to implement all the business process requirements based on the Business Blueprint. The system configuration methodology is provided in two work packages: Baseline (major scope); and Final configuration (remaining scope). Other key focal areas of this phase are conducting integration tests and drawing up end user documentation.

    Final Preparation: The purpose of this phase is to complete the final preparation (including testing, end user training, system management and cutover activities) to finalize your readiness to go live. The Final Preparation phase also serves to resolve all critical open issues. On successful completion of this phase, you are ready to run your business in your live SAP System.

    Add a comment
    10|10000 characters needed characters exceeded

  • author's profile photo Former Member
    Former Member
    Posted on Aug 11, 2009 at 05:58 AM

    Hi,

    In Realization phase we will do the all kind of testing and the Final preparation is mainly for Data migration, end user training and cutover activities and to finalize your readiness to go live. The Final Preparation phase also serves to resolve all critical open issues.

    Add a comment
    10|10000 characters needed characters exceeded

Before answering

You should only submit an answer when you are proposing a solution to the poster's problem. If you want the poster to clarify the question or provide more information, please leave a comment instead, requesting additional details. When answering, please include specifics, such as step-by-step instructions, context for the solution, and links to useful resources. Also, please make sure that you answer complies with our Rules of Engagement.
You must be Logged in to submit an answer.

Up to 10 attachments (including images) can be used with a maximum of 1.0 MB each and 10.5 MB total.