Hi,

can we assign a multiple planned order into single production order for the same material and same bom.

Is there possible.

Otherwise can we group planned order for different plant.

Rgds]

bhuvaneswaran

Accepted Solutions (0)

Answers (3)

Answers (3)

rupesh_brahmankar3
Active Contributor
0 Kudos

Dear,

It is possible in IS Mill You need to use T code :Mill_OC is to create combined order & group the orders.

Please refer this link for details,

[Combination Order|https://www.sdn.sap.com/irj/scn/weblogs?blog=/cs/junior/view/wlg/15188]

Regards,

R.Brahmankar

former_member184655
Active Contributor
0 Kudos

Dear Bhuvaneshwaran,

In standard SAP it's not possible to generate one single production order by using multiple planned orders.

The T Code What Mr.Krishanprasad has mentioned is to convert planned order's collectively into production order's which does

not mean,one single production order.

Check and revert back.

Regards

Mangalraj.S

Former Member
0 Kudos

Hi

use Co41 t.code and select the planned order to be converted and click on convert and later mention the order no. This way u can convert planned orders into one production order

krishna