on 08-10-2009 1:12 PM
Hi
I want to upload a project to SAP from MS project through Open PS. Though PD and WBS element are getting succesfully uploaded, but could not be the network.How is it possible??
Zinni
Zinni,
In MS projects there is nothing called networks. Activities are defined as tasks. While uploading through OPEN PS to identify the network activities you need to define the CONTROL KEY, MRP controller, Object type (as NetworkActivity), Network type, WBS element columns in project activity rows.
rgds
saurabh