on 08-10-2009 8:43 AM
u2022Do coverage profiles only look at actual requirements in the coming weeks or do they look at forecast as well.
u2022Does coverage profile work with only some specific MRP types and not others
Difference between coverage profile and service level in MRP2 view of material master.
u2022What lot-sizing procedure should be used with Coverage profiles
u2022If I am using Coverage profile, I shouldnu2019t be using Service level, right
answered
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Q1u2022Do coverage profiles only look at actual requirements in the coming weeks or do they look at forecast as well.
Ans: 1. Coverage profiles looks at the actual requirements whichever are considered to be part of the planning.
u2022Does coverage profile work with only some specific MRP types and not others
Ans: 1. It have used with Mrp type pd,p1top4. for others we need to check it.
u2022What lot-sizing procedure should be used with Coverage profiles
Ans: any lot sizing can be used.
Kindly avoid, multiple questiosn in one thread
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.