OKB9 Profit center wise assignment is not allowing.

Former Member
0 Kudos

Dear Experts,

Here iam facing problem like, In OKB9 setting valuation area wise allowing for cost center assignment, Profit Center wise not allowing for cost center assignment.It means it will allow to assign cost centers, but while transacting error troughing like co object missing, if we make setting like valuation area, it not throughing any error.

We can think why cant we go for assignment with valuation area.But we have number of profit centers under one plant, Plant is equal to valuation area, Here iam suppose to go by profit center wise only, please give me a better solution to come out of this issue at the earliest.

Thanking u in advance

Chinni

Accepted Solutions (0)

Answers (2)

Answers (2)

Former Member
0 Kudos

clear

Former Member
0 Kudos

Hi,

Select 3 in account assignment i.e. Profit Center Mandatory and then give profit center in combination of Cost Center.

May also I know why do u have multiple Profit Centers in a single plant? Generally u can create one profit center for one plant and there by u assign for material and plant combination this profit center. If u follow this process then u can use 1(Valuation area) as mandatory and assign the profit centers/cost centers for each plant.

Regards

Sudhakar Reddy

Former Member
0 Kudos

Dear,

Thanks for ur immediate responce, Here we have different products in the same plant, they want to see for such material differently, not for all, but only one in plant.Give me best suggestion if anything wrong.As u said already i have assigned that 3, but it is throughing error at the time of posting.

Please clear me how to overcome this issue.

Thanks,

chinni

Former Member
0 Kudos

Hi,

Try to work it out Substitution rule in OKC9..

Regards

Sudhakar Reddy