Skip to Content
0
Former Member
Aug 07, 2009 at 03:32 PM

SNP PDS effectivity date in the future

77 Views

I have an SNP PDS for a new resource that will start production some time in the future. I do not want to use that resource until that later date. So I set the valid from date on the production version in R/3. That CIFed over fine and the source of supply actually worked as expected. Howver the PDS had no resource. I found OSS note 1138338 that says.

"The operations, activities, mode and resources are not transferred to APO for SNP-PDS and CTM-PDS if the "valid from date" of the production version is in the future."

Since I can not edit PDS directly in APO. This limits my solution options.

I have tried a time phased quota arrangement.

Has anyone else encountered this problem and what did you do to get around it.

Thanks for the help.

George Morstadt