I have an end product which require 5 sub materials to produce, 4 sub items are supplied by me and one subcontractor is using from his own.

I have a BOM for it. Where in BOM I can specifiy that the the item will be used by the subcontractor and will not be provided by me to him.

Can I specify this in PO if the BOM doesnot have the provision ?

I have to make it clear in the PO what will be provided by me and what will be used by subcontractor

Add a comment
10|10000 characters needed characters exceeded

Related questions

5 Answers

  • Best Answer
    author's profile photo Former Member
    Former Member
    Posted on Aug 07, 2009 at 07:37 PM

    In subcontract purchase order(item category is 'L') enter the finished product in PO. On bottom section item detail go to material data tab. Click on components icon (right side of screen). You must be in create me21n or change mode me22n. The components icon brings up the default components from the BOM. In this screen you can delete the material that the vendor is suppling. Select the line to remove and go to top EDit -->Delete.

    If you are going to do this often, you can set up a purchasing info record with an alternate BOM without this item and the alternate bom will get picked up when create a PO for the vendor/finished material/plant.

    Hope this helps

    Add a comment
    10|10000 characters needed characters exceeded

  • author's profile photo Former Member
    Former Member
    Posted on Aug 07, 2009 at 12:14 PM

    You can use the Text Tabs at Header Level or Item Level ...

    Add a comment
    10|10000 characters needed characters exceeded

  • author's profile photo Former Member
    Former Member
    Posted on Aug 07, 2009 at 12:23 PM

    Hi,

    If it is one time, then you indicate in the PO text. If it is going to be regular with this Vendor, then you create Production Version and indicate in the Sub-contracting Info record. During the S/c PO ... this new BOM will explode and get you list of those components which will be delivered to that Vendor.

    Best Regards,

    Suresh

    Add a comment
    10|10000 characters needed characters exceeded

  • author's profile photo Former Member
    Former Member
    Posted on Aug 07, 2009 at 12:34 PM

    Dear Friend,

    For this my solution is not to maintain that material in the BOM and raise the purchase order with respect to cost centre for that material or add the price of that material in the service charge itself

    Only what are the material your sending to him those material only you maintain in the BOM and send in subcontracting PO to that vendor,

    Regards

    pramod

    Add a comment
    10|10000 characters needed characters exceeded

    • Former Member

      If I understood rightly, in the subcontracting BOM there is no provision to add the components that are used by subcontractor.

      It has to be as a separate line item in PO or a separate PO. Or can be included along with the cost of service.

  • author's profile photo Former Member
    Former Member
    Posted on Aug 13, 2009 at 08:55 AM

    doubts cleared

    Add a comment
    10|10000 characters needed characters exceeded

Before answering

You should only submit an answer when you are proposing a solution to the poster's problem. If you want the poster to clarify the question or provide more information, please leave a comment instead, requesting additional details. When answering, please include specifics, such as step-by-step instructions, context for the solution, and links to useful resources. Also, please make sure that you answer complies with our Rules of Engagement.
You must be Logged in to submit an answer.

Up to 10 attachments (including images) can be used with a maximum of 1.0 MB each and 10.5 MB total.