material used by subcontractor in subcontracting process

Former Member
0 Kudos

I have an end product which require 5 sub materials to produce, 4 sub items are supplied by me and one subcontractor is using from his own.

I have a BOM for it. Where in BOM I can specifiy that the the item will be used by the subcontractor and will not be provided by me to him.

Can I specify this in PO if the BOM doesnot have the provision ?

I have to make it clear in the PO what will be provided by me and what will be used by subcontractor

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

In subcontract purchase order(item category is 'L') enter the finished product in PO. On bottom section item detail go to material data tab. Click on components icon (right side of screen). You must be in create me21n or change mode me22n. The components icon brings up the default components from the BOM. In this screen you can delete the material that the vendor is suppling. Select the line to remove and go to top EDit -->Delete.

If you are going to do this often, you can set up a purchasing info record with an alternate BOM without this item and the alternate bom will get picked up when create a PO for the vendor/finished material/plant.

Hope this helps

Former Member
0 Kudos

Thanks

My question was that in BOM can i specify both the items as supplied by me and not supplied by me.

what i have understood from the replies of other is that in subcontacting BOM that cannot be specified. Rather the item used by subcontractor is to be procured separately in PO or can be considered to be in the cost of servcie charged.

raviraj_sharma
Active Contributor
0 Kudos

Yes , you are correct.

Answers (4)

Answers (4)

Former Member
0 Kudos

doubts cleared

Former Member
0 Kudos

Dear Friend,

For this my solution is not to maintain that material in the BOM and raise the purchase order with respect to cost centre for that material or add the price of that material in the service charge itself

Only what are the material your sending to him those material only you maintain in the BOM and send in subcontracting PO to that vendor,

Regards

pramod

Former Member
0 Kudos

If I understood rightly, in the subcontracting BOM there is no provision to add the components that are used by subcontractor.

It has to be as a separate line item in PO or a separate PO. Or can be included along with the cost of service.

Former Member
0 Kudos

Hi,

If it is one time, then you indicate in the PO text. If it is going to be regular with this Vendor, then you create Production Version and indicate in the Sub-contracting Info record. During the S/c PO ... this new BOM will explode and get you list of those components which will be delivered to that Vendor.

Best Regards,

Suresh

Former Member
0 Kudos

You can use the Text Tabs at Header Level or Item Level ...