Selection BOM alternative when run on Long-term Planning

Former Member
0 Kudos

Dear experts,

I have some question, I've 2 production version, prd.vers.1 for production and prd.vers. 2 for run long-term for budgeting(Long-term planning).

When i run MS02 i want SAP select production version 2 to generate an activity.

How to make SAP selected production version 2 for MS02?

Thank you

Accepted Solutions (0)

Answers (1)

Answers (1)

Caetano
Product and Topic Expert
Product and Topic Expert
0 Kudos

Hello

In the planning scenario (MS32) you can define a specific BOM selection ID. In this case, you can force LTP to select a specific bill of material.

Otrherwise, you can use BAdI MD_MODIFY_PRODVERS to implement your own logic for production version selection.

Regards,

Caetano