Financial values are not transfer to PS Project and WBS element

0 Kudos

Hi Experts,

In my scenario , I am integrating PPM Item and PS project. On save, I am able to replicate the project in PS system . When I am trying to transfer financial values to PS project, cost is not transferring. I am not getting any error message also. Any solution please .

I am slecting "Transfer" checkbox also.

Thanks & Regards

Rama Shanker untitled.png

Accepted Solutions (0)

Answers (1)

Answers (1)

francesco_pezzoli
Active Participant
0 Kudos

Hello Rama Shanker,

The reported behaviour could be caused if the mapping in customizing activity "Define Financial Planning Settings" does not cover the View/Category/Group for which you want to transfer the values to ERP.

I would recommend that you check this customizing (SAP Portfolio and Project Management > Portfolio Management > Base System Interfaces > Financial Planning Settings > Define Financial Planning Settings) to ensure that the mapping is correct.

Regards

Francesco