Can we update the time profile records post planning area activation?

0 Kudos

Is updating the time profile records post planning area activation possible?

Accepted Solutions (1)

Accepted Solutions (1)

ayanbishnu1981
Active Contributor
0 Kudos

If it is just about generating time periods for the time profile, yes you can update it post planning area activation. But if you are referring to add a new time bucket or remove an existing time bucket, then the answer is no.

Thank you Ayan!

Answers (1)

Answers (1)

anil_gupta8
Active Participant
0 Kudos

In my opinion yes if you are not adding any more attribute to time profile than yes. I hope you chose the option to down load time profile with existing period . What exactly you want to do when you mention updating time profile