Hi Guys,
Can you please help we with the solution to set deletion indicator in purchase requisition account assignment or close purchase requisition. A purchase requisition of $3.600.000,00 was created through Project system Network-External Processing and it has 2 duplicate network activities and $2.246.577,20 was converted to purchase order then $1,353,423 became the network remaining order plan. A purchase order service entry sheet was accepted and the invoice was created. Now Iu2019m experiencing problem when Iu2019m trying to change WBS element and Network system status to TECO in order to remove the remaining order plan of $1,353,423. Iu2019m getting error message number:06411 the procedure I have follow to correct the error is to reduce quantities in the account assignment item and delete superfluous account assignment by setting deletion in each case but I cannot do that because the fields are grey