Adding resources to WBS elements / projects

Former Member
0 Kudos

Hello,

I am trying to add a resource to a WBS element in an SAP test system, but am having some difficulty finding the correct transaction as the Fi lead is away. I normally specialise in HR and am not familiar with the Fi Co transactions...

I already have the user and the WBS element, so just need to find the transaction that will assign the user to the WBS!

Please could somebody help to point me in the right direction? I don't imaging that it is very hard to do, but some help would be much appreciated.

Regards,

Euan

Accepted Solutions (0)

Answers (1)

Answers (1)

Paulo_Vitoriano
Active Contributor
0 Kudos

From the Project Builder (CJ20N) you switch to the Project Planning Board (Shift + F8), in the menu Goto - Capacity Levelling - Workforce planning, select Wkf Planning profile, and you are there.

Or try CMP2/CMP3.