Easily modifying task structure in a project

Former Member
0 Kudos

Hello,

My users have come up with a question. I do not have a wonderful answer for them, so I thought I would post here to see if there are any ideas.

My users are used to using Microsoft Project client in which you can easily indent and outdent tasks or cut/copy/paste. Is there an easy way in cProjects to outdent/indent tasks in the project hierarchy?

Also, once tasks are released we can't move them from one section to the project to another. Would there be a way to do this also?

Thank you!

Wendy

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

The cut/copy/paste feature does exist in cProject. The icons in the top of the project structure pane provide this functionality.

Indenting in the way MS Projects implements it is not supported in cProjects. Also moving or deleting tasks after releasing them is not supported in cProjects.

Regards,

Debaranjan Hazarika.

Answers (3)

Answers (3)

thomas_berndt
Active Participant
0 Kudos

Hello Wendy,

I'm afraid what Debaranjan wrote above is true. There's no indent/outdent in cProjects.

And cut&paste can be used to some extend to mimiq that, but in a rather cumbersome way.

Best regards,

Thomas

Former Member
0 Kudos

hi,

The mentioned functianlity is not there in standard SAP cProjects. However I feel you should try to do MSP & cProjects integration to meet the above functionality (except task deletion).

Regards,

Pramod

Former Member
0 Kudos

hi

cProjects does not have this functionality