CHANGE REQUESTS tab missing under SOLAR_PROJECT_ADMIN

Hello All,

Am trying to configure CHARM in our SolMan system. I referred to the below link for configuration.

/people/dolores.correa/blog/2008/07/26/first-steps-to-work-with-change-request-management-scenario

I am trying to create a project under tcode: SOLAR_PROJECT_ADMIN

while creating project with in SYSTEM LANDSCAPE tab we can see FOLLOWING

SYSTEMS /\ CENTRAL OBJECTS /\ IMG PROJECTS .

But am unable to see CHANGE REQUESTS tab which should be at last in the above mentioned sequence .

can any 1 tell me why its not there. Do i need to configure anything more to get the CHANGE REQUESTS tab

Regards,

Ravi

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

2 Answers

  • Best Answer
    avatar image
    Former Member
    Aug 03, 2009 at 06:54 PM

    Hi,

    You need to activate the bussiness sets. Have you done that?

    This blog doesn't sppek about activating BC sets.

    Activate the BC sets as per the note: Note 903527 - Solution Manager Change Management: BC setsu2019

    Regards,

    Vamshi.

    Add comment
    10|10000 characters needed characters exceeded

  • avatar image
    Former Member
    Aug 04, 2009 at 12:35 PM

    Hello,

    i had the same problem few weeks ago. I couldn't find the Change request Tab in Solar_project_admin

    I fixed it by following : SAP note : 802793

    The note explain how to re assign the client to manage change request management.

    We folow the note, then the missing tab appear 😊