on 08-03-2009 6:15 PM
Hello All,
Am trying to configure CHARM in our SolMan system. I referred to the below link for configuration.
/people/dolores.correa/blog/2008/07/26/first-steps-to-work-with-change-request-management-scenario
I am trying to create a project under tcode: SOLAR_PROJECT_ADMIN
while creating project with in SYSTEM LANDSCAPE tab we can see FOLLOWING
SYSTEMS /\ CENTRAL OBJECTS /\ IMG PROJECTS .
But am unable to see CHANGE REQUESTS tab which should be at last in the above mentioned sequence .
can any 1 tell me why its not there. Do i need to configure anything more to get the CHANGE REQUESTS tab
Regards,
Ravi
Hi,
You need to activate the bussiness sets. Have you done that?
This blog doesn't sppek about activating BC sets.
Activate the BC sets as per the note: Note 903527 - Solution Manager Change Management: BC setsu2019
Regards,
Vamshi.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hello,
i had the same problem few weeks ago. I couldn't find the Change request Tab in Solar_project_admin
I fixed it by following : SAP note : 802793
The note explain how to re assign the client to manage change request management.
We folow the note, then the missing tab appear
Regards
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
85 | |
10 | |
10 | |
9 | |
7 | |
7 | |
6 | |
5 | |
4 | |
4 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.