Dear Experts,

I am having a situation as follows:

1. Budget Avalibility check is getting triggered at Project(Ex: A1) level when raising a PO which is raised based on reservations made against a WBS Element(Ex: A1-1) of the same project.

2. But the Budget Avalibility check is not getting triggred when raising a PO which is raised based on reservations made against a Maintance Order (in Plant Maintance) which is funded by the WBS Element (A1-1).

My Concern is does we have to activate availability check seperatley for the second senario ?

Very Much Appreciate your Guidance,