Hi All,

The scenario is below. In the material master, the procurement type is F with special procurement 30. Now we are going to change that as E without any special procurement. So if I run MRP, Planned Orders will be created for unfirmed PR,s and for new requirements. But what happens to the firmed PR's and Open Subcontracting PO's ?
Will I be able to continue the old process for the existing firmed PR's and open PO's ??

Add comment
10|10000 characters needed characters exceeded

  • Follow
  • Get RSS Feed

1 Answer

  • Sep 18, 2018 at 11:26 AM

    Hello

    MRP will not change firmed purchase requisitions and purchase orders, even if you change your master data.

    You need to manually close those orders, so that MRP can generate new planned order to cover the requirements.