cancel
Showing results for 
Search instead for 
Did you mean: 

BOM need to be half for costing calculation

Keshi1
Active Participant
0 Kudos

Hi

I need to calculate the standard cost taking half a alue fro m the standard BOM. So I choice CO02 --> status --> costing relevancy 50%.

But when i carry out the costing run it doesn't show the half in values.

Do I have to do any configuration or changes to tale the half form the BOM for cost calculation.

Thanx in advance

K

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Hi

The Following SPRO Settings required to Use Costing relevancy like 25%,50 % , 75 % or any defined % other than 100 % or 0 %

1) In the Costing Variant the Costing type should be Inv. costing - tax law or Inv. costing - commer.law it can not work with Standard cost est. (mat.)

2) Define Price Factors in OKK7 and assign this PF in Valuation Variant

If you carry the Costing run with the Costing variant then the Costing relevancy will reflect in Itemization with the relevancy choosen in BOM item details

Pl refer SAP Links for More details

http://help.sap.com/saphelp_45b/helpdata/en/c3/e62c7dd435d1118b3f0060b03ca329/content.htm

Regards

Brahmaji

Answers (0)